Manager’s Messages
Paint Project
Dear Eastern Resident, Exterior Paint Project Update: The scaffolding for the paint project is scheduled to be installed at the back of the building (Hill Street side) on 2/28. It will be erected on the ground floor and run the entire width of the building including the patios of units 101 and 102. It is said to take two days to install. The swing stage will then be delivered on 3/3 and will be installed on the pool deck. This will be used to drop down the sides of the building for the prep and painting work. We will provide specific drop schedules very soon. All items will need to be removed from the balconies before they get to your drop, so please stay tuned for the specific drop schedule. We appreciate your patience during these very important projects. Best Regards, Brandon Patterson, CCAM-HR General Manager |